Bogie exchange facility

Bogie exchange facility

Bogie exchange facility

Objectives

  • This facility enables to separate/move/replace the inspection subject toward underground pit at the bottom of the vehicle for fast maintenance work with separated bogie instead of lifting 1~2 bogie, wheelset, and traction motor simultaneously in KTX train set (20 cars: 400m approximately) state.

Main components

  • Dropping table main body (max. 400kN), supporting jack(4개*250kN), rail hatch, control board/pendant
  • Dropping table / hydraulic power pack / driving gear

    Dropping table / hydraulic power pack / driving gear

  • Supporting jack (4 jacks)

    Supporting jack (4 jacks)

  • MCB

    Rail hatch

  • MCB

    Control board and pendant

Job sequence

  • Dropping table waiting on the bogie exchange line Dropping table waiting on the bogie exchange line
  • Rolling Stock enters to the bogie exchange line Rolling Stock enters to the bogie exchange line
  • Support the rolling stock with supporting jacks Support the rolling stock with supporting jacks
  • Open the rail hatch and move the bogie to the workplace Open the rail hatch and move the bogie to the workplace
  • Descend the separated bogie and move it toward rail hatch line Descend the separated bogie and move it toward rail hatch line
  • Separate devices including bogie from the bottom of the vehicle while it is supported Separate devices including bogie from the bottom of the vehicle while it is supported

Job process outline