TitleKorea Rail Network Authority launches electricity installation in earnest in the Seongnam ~ Yeoju railroad construction section

□ The Korea 
Rail Network Authority’s Capital 
Area Office (Chief Su-hyeong Lee) announced that it would push for construction 
in earnest from October and complete the construction in the first half of 2016 
after it established a contract on electricity installation that is a follow-up 
process in the Seongnam ~ Yeoju Double Track Line Construction. 

○The electricity installation aims to supply the electricity (25kV) 
required to operate trains, and a total of 49.7 billion won is invested. The 
installation is divided into one railroad electricity section, two railroad 
line sections and one electric power section.